  • NHIDCL updates ongoing projects in Meluri district


    The ongoing widening to 2 lanes with a hard shoulder from Km 69 to Km 106 of the Akhegwo-Avangkhu section on NH-202.


  • DIMAPUR — The National Highways & Infrastructure Development Corporation Ltd. (NHIDCL) has updated its ongoing projects ‘Sculpting smooth roads for driving dreams’ for NH-202 (Akhegwo-Jessami section) and NH-202K (Akhegwo-Avangkhu section) in Meluri district.

  • As per the NHIDCL, the “Widening to 2-Lane with hard shoulder of Akhegwo-Avangkhu section of NH-202K for Package-I (Design Chainage 0+000 Km to 34+795 Km) in the State of Nagaland on EPC mode under NH-NE” is under construction and scheduled to be completed on February 23, 2026. The total length of the project is 34.7955 km.

  • The project, handed over to Mayasheel Construction JSP Projects Pvt. Ltd. (JV) at a total cost of INR 430.24 crore, has made 49.95% physical progress and 49.1% financial progress. The project was awarded in March 2023 and appointed on August 24, 2023.


NHIDCL updates ongoing projects in Meluri district

  • The ongoing widening to 2 lanes with a hard shoulder from Km 69 to Km 106 of the Akhegwo-Avangkhu section on NH-202.


  • The ongoing “Widening to 2-Lane with hard shoulder of Akhegwo-Avangkhu section of NH-202K for Package-II (Design Chainage 34+795 Km to 69+875 Km)” project is also scheduled to be completed by February 23, 2026.


Also read: NHIDCL updates progress on Peren-Dimapur highway construction


  • Awarded to Kantilal Khimjibhi Bhalala Project Pvt. Ltd. (KKB) on February 8, 2023, and appointed on June 24, 2023, at a cost of INR 442.54 crore with 35.08 km as the total length, the project has made physical progress of 20.85% and financial progress of 18.11%.

  • Another ongoing project on NH-202K, “Widening to 2-Lane with hard shoulder of Akhegwo-Avangkhu section of NH-202K for Package-III (Design Chainage 69+875 Km to 106+816 km)”, has made a physical progress of 59.2%.

  • The project awarded to New India Contractors & Developers Pvt. Ltd. - Bharat Construction Co. (JV) at a cost of INR 497.18 crore has made financial progress of 58.46%. The project was awarded on Feb. 8, 2023, and appointed on Aug. 26, 2023. With a total length of 36.941 km, the project is scheduled to be completed on Feb. 25, 2026.

  • The project on NH-202 under package I, “Construction of 2-lane with hard shoulder from Design Chainage Km 283.000 to Km 325.440 (5-legged junction at Old Akhegwo) to (Akash Bridge) of Akhegwo-Jessami section of NH-202 (Package-I) [Nagaland Portion]”, has been completed as per the projected date on Jan. 17, 2025.

  • The 42.44 km project was awarded to Kantilal Khimjibhi Bhalala Project Pvt. Ltd. (KKB) - YN Dhanani (YND) (JV) at a cost of INR 605.36 crore. Awarded on March 30, 2022, the project was appointed on June 23, 2022.