- DIMAPUR — The National Highways &
Infrastructure Development Corporation Ltd. (NHIDCL) has updated its ongoing
projects ‘Sculpting smooth roads for driving dreams’ for NH-202
(Akhegwo-Jessami section) and NH-202K (Akhegwo-Avangkhu section) in Meluri
district.
- As per the NHIDCL, the “Widening to 2-Lane with hard
shoulder of Akhegwo-Avangkhu section of NH-202K for Package-I (Design Chainage
0+000 Km to 34+795 Km) in the State of Nagaland on EPC mode under NH-NE” is
under construction and scheduled to be completed on February 23, 2026. The
total length of the project is 34.7955 km.
- The project, handed over to Mayasheel Construction JSP
Projects Pvt. Ltd. (JV) at a total cost of INR 430.24 crore, has made 49.95%
physical progress and 49.1% financial progress. The project was awarded in
March 2023 and appointed on August 24, 2023.

The ongoing widening to 2 lanes with a hard shoulder from Km
69 to Km 106 of the Akhegwo-Avangkhu section on NH-202.
- The ongoing “Widening to 2-Lane with hard shoulder of
Akhegwo-Avangkhu section of NH-202K for Package-II (Design Chainage 34+795 Km
to 69+875 Km)” project is also scheduled to be completed by February 23, 2026.
Also read: NHIDCL updates progress on Peren-Dimapur highway construction
- Awarded to Kantilal Khimjibhi Bhalala Project Pvt. Ltd.
(KKB) on February 8, 2023, and appointed on June 24, 2023, at a cost of INR
442.54 crore with 35.08 km as the total length, the project has made physical
progress of 20.85% and financial progress of 18.11%.
- Another ongoing project on NH-202K, “Widening to 2-Lane with
hard shoulder of Akhegwo-Avangkhu section of NH-202K for Package-III (Design
Chainage 69+875 Km to 106+816 km)”, has made a physical progress of 59.2%.
- The project awarded to New India Contractors &
Developers Pvt. Ltd. - Bharat Construction Co. (JV) at a cost of INR 497.18
crore has made financial progress of 58.46%. The project was awarded on Feb. 8,
2023, and appointed on Aug. 26, 2023. With a total length of 36.941 km, the
project is scheduled to be completed on Feb. 25, 2026.
- The project on NH-202 under package I, “Construction of
2-lane with hard shoulder from Design Chainage Km 283.000 to Km 325.440
(5-legged junction at Old Akhegwo) to (Akash Bridge) of Akhegwo-Jessami section
of NH-202 (Package-I) [Nagaland Portion]”, has been completed as per the
projected date on Jan. 17, 2025.
- The 42.44 km project was awarded to Kantilal Khimjibhi
Bhalala Project Pvt. Ltd. (KKB) - YN Dhanani (YND) (JV) at a cost of INR 605.36
crore. Awarded on March 30, 2022, the project was appointed on June 23, 2022.